Nonconformance Report Example: A Filled-In NCR

A good nonconformance report states the requirement and the measured result side by side, says how much product is affected and where it is now, and records who decided the disposition and why. Below is a complete NCR for a fictional receiving inspection reject, filled in field by field in the order of our free NCR form: header, part and lot, requirement vs actual, containment, disposition, root cause and CAPA reference, corrective action, and sign-off. Each step explains what to enter and what the example entered.

By Coplain Team

Last updated

Step by step

  1. Fill in the header — give the NCR a unique number, the date opened, who found it and where (receiving, in-process, final, customer return or audit). The example: NCR-0412, opened 2026-10-06 by the receiving inspector, source receiving inspection. Use the NCR form so every report has the same fields.
  2. Identify the part and lot — enter part number and revision, lot or batch, purchase order, supplier and quantity received. The example: spacer SP-220 rev C, supplier lot 7731, PO 5518, 500 pieces received. Without the revision and lot, nobody can trace which product is affected.
  3. State requirement vs actual — quote the drawing or specification reference, the requirement and the measured values, with the gauge used. The example: drawing SP-220 rev C requires thickness 3.00 ± 0.05 mm; measured 3.07 to 3.11 mm on 4 of 50 sampled pieces with a calibrated micrometer. The NCR writing guide covers how to phrase this field.
  4. Record containment — say where the suspect product is, how it is identified and whether any already moved on. The example: lot tagged HOLD tag 0981 and moved to the quarantine rack; stock check found no earlier SP-220 receipts from this lot in production.
  5. Record the disposition and who approved it — choose use as is, rework, repair, scrap or return to supplier, and write the reason and the authority. Use as is and repair usually need MRB and sometimes customer approval. The example: 100% sort, return the rejects to the supplier, accept the rest; approved by the quality engineer.
  6. Reference the root cause and any CAPA — write a short cause statement if it is known, and decide whether the problem needs a full corrective action. For a supplier cause, issue a SCAR and reference its number. For an internal cause, open a CAPA and run a 5 Whys.
  7. Set the follow-up on the next receipts — state what will change until the cause is proven fixed, with an owner and a date. The example: tightened inspection on the next three SP-220 lots, owner receiving lead, review on 2026-11-30.
  8. Sign off and close — close the NCR only when the disposition is complete and the records are attached: sort results, return paperwork, SCAR reference. A CAPA or SCAR can stay open after the NCR closes.

What ISO 9001 expects the NCR to hold

ISO 9001 clause 8.7 asks you to identify and control outputs that do not conform so they are not used or delivered by accident, and to deal with them by correction, segregation, return, informing the customer or accepting them under concession. It also asks you to keep records that describe the nonconformity, the actions taken, any concessions, and who decided what to do. The example covers each of those: the description field, the containment and disposition fields, and the approval.

IATF 16949 and AS9100 add their own requirements, such as customer authorization before shipping product under concession. Medical device makers have similar expectations under FDA’s Quality Management System Regulation. Check your customer requirements before you choose use as is or repair.

Why the sampling numbers belong on the NCR

A receiving reject is a decision about the whole lot based on a sample, so the NCR should show the plan and the result. Record the sample size, the accept and reject numbers and how many nonconforming pieces were found. Anyone reviewing the NCR can then check the decision without asking. Find the sample size for your lot with the AQL sampling calculator, confirm the accept and reject numbers against ANSI/ASQ Z1.4 or the plan in your receiving procedure, and keep the inspection steps on a receiving inspection checklist.

After a 100% sort, record the sorted count too. It sets the quantity for the return, gives the supplier a fact to work from in their response, and shows whether the problem was a few stray parts or a whole run.

NCR, SCAR and CAPA: who owns what

The NCR deals with the product in hand. A SCAR asks the supplier to find and fix their cause. A CAPA is your own corrective action, for causes inside your process or your supplier management. One event can produce all three, each with its own number and closure, cross-referenced on the NCR.

Track open actions in a corrective action log, and treat repeat NCRs on the same part or supplier as a signal that the earlier cause was not fixed. The CAPA guide covers when an NCR should escalate.

Worked examples

Example: NCR-0412, receiving inspection at a fictional assembly shop. Spacer SP-220 rev C, supplier lot 7731, 500 pieces. Requirement: thickness 3.00 ± 0.05 mm (2.95 to 3.05 mm). The receiving procedure’s plan for 281 to 500 pieces at AQL 1.0 is: sample 50, accept on 1 nonconforming, reject on 2.

  1. Sample: 50 pieces measured. Nonconforming: 4 pieces at 3.07, 3.08, 3.09 and 3.11 mm, all over the 3.05 mm upper limit
  2. Decision: 4 found is at or above the reject number of 2, so the lot is rejected
  3. Sample nonconforming rate: 4 ÷ 50 = 8.0%
  4. Containment: lot on HOLD tag 0981 in quarantine; no pieces from lot 7731 issued to production
  5. Disposition: 100% sort of 500 pieces approved by the quality engineer instead of returning the whole lot, because the line needs parts
  6. Sort result: 37 pieces over 3.05 mm, 463 within 2.95 to 3.05 mm. Lot nonconforming rate: 37 ÷ 500 = 7.4%
  7. Check: 463 + 37 = 500, so every piece is accounted for
  8. Action: 37 pieces returned to the supplier on return authorization RA-2290; 463 released to stock with the sort record attached
  9. Cause and follow-up: supplier cause suspected (material thickness); SCAR-0087 issued. Tightened inspection on the next three SP-220 lots, review 2026-11-30
  10. Closure: NCR closed 2026-10-09 after the return and release; SCAR-0087 stays open until the supplier’s action is verified

Result: The NCR shows the requirement and the measurements side by side, the sampling decision, where every one of the 500 pieces went, who authorized the sort, and the link to the supplier corrective action. A reviewer can check each decision from the record alone.

Common mistakes

Frequently asked questions

What should a nonconformance report include?

An NCR number and date, the part, revision and lot, the requirement and the measured result, quantity affected, containment, disposition with approval, root cause or a CAPA or SCAR reference, and closure sign-off.

Who fills out an NCR?

Whoever finds the nonconformance opens it, often an inspector or operator. Quality usually completes the disposition and root cause fields, and an MRB or the customer approves dispositions such as use as is.

Does every NCR need a CAPA?

No. Open a CAPA when the problem is serious, repeats, or has a cause in your own system. A one-off supplier defect is often handled through a SCAR referenced on the NCR.

How long should an NCR stay open?

Until the affected product has been dispositioned and the evidence is attached. Many companies set a target of days, not weeks, and track the corrective action separately.

Can I use this example as a template?

Use the free NCR form for the layout and this example as a guide to the level of detail. Replace the fictional numbers with your own requirement, measurements and references.

Sources

  1. ISO 9001:2015 Quality management systems — Requirements (clause 8.7), ISO
  2. ANSI/ASQ Z1.4 Sampling Procedures and Tables for Inspection by Attributes, ASQ
  3. IATF 16949:2016 Automotive quality management system standard, IATF
  4. 21 CFR Part 820, Quality Management System Regulation, U.S. Food and Drug Administration

See also

COPLAIN AI PLATFORM

Generate yours automatically from your existing docs

Describe the nonconformance and Coplain drafts the NCR with the requirement, containment and disposition fields filled in, ready for your quality engineer to review.

Generate yours automatically with Coplain →

Related Tools & Templates