TEMPLATESAUDIT SCHEDULEFree Excel (.xlsx) download

Internal Audit Schedule Template

An Excel audit programme with one row per process. Rate each process by risk and importance, and the sheet sets the audit interval, calculates the next due date, flags overdue and upcoming audits, and catches auditors scheduled on their own work.

Who this template is for

Quality managers and internal audit coordinators who plan the audit programme for an ISO 9001, IATF 16949 or AS9100 system, and the auditors who work from it.

When to use it

Standards it supports

How to use this template

  1. List the processes — use your process map or turtle diagrams so every QMS process, shift and site appears once.
  2. Set the intervals — enter how many months between audits for High, Medium and Low processes at the top of the sheet.
  3. Rate each process — choose High, Medium or Low from importance, past results, changes and complaints; the interval follows.
  4. Enter the last audit and auditor — enter the date of the last audit and the lead auditor, and confirm they do not audit their own work.
  5. Work the status column — audit Overdue rows first, plan the Due within 30 days rows, and update the last audit date when each audit is done.

Tip: The as-of date uses TODAY() on the blank sheet, so the status updates each time you open it. Overwrite it with a fixed date to print a snapshot.

What's inside the template

1

Header

Company, as-of date, interval in months for High, Medium and Low, programme owner

2

Scope

Process or area, clauses covered and process owner

3

Risk and interval

Risk and importance rating with the calculated interval

4

Dates

Last audited, calculated next due date and planned month

5

Auditor

Lead auditor and an independence check

6

Status and summary

Overdue, due within 30 days, scheduled or not yet audited, with counts

Example: a completed template

Example Audit programme for Example Precision Co., a fictional machine shop, as of 2026-10-01. Intervals: High 6 months, Medium 12, Low 24. Processes, dates and roles are invented for illustration.

Programme

ProcessClausesRiskLast auditedNext dueLead auditorIndependentStatus
Sales and contract review8.2Medium2025-11-122026-11-12Quality EngineerYesScheduled
Purchasing and supplier control8.4High2026-03-182026-09-18Quality ManagerYesOverdue
Production (CNC)8.5.1, 8.5.2, 8.7High2026-04-202026-10-20Quality EngineerYesDue within 30 days
Measurement and calibration7.1.5Medium2026-02-102027-02-10Operations ManagerYesScheduled
Training and competence7.2, 7.3Low2025-06-052027-06-05Quality EngineerYesScheduled
Internal audit and management review9.2, 9.3Medium——Operations ManagerYesNot yet audited
Document control7.5Low2025-01-152027-01-15Quality ManagerNoScheduled

Summary

Processes7
Overdue1
Due within 30 days1
Not yet audited1
Auditor not independent1 (the Quality Manager auditing document control)

The math in this Example

How to fill in each field

FieldWhat to enterExample
As ofTODAY() on the blank sheet. Every status is calculated against it.2026-10-01
Interval (High / Medium / Low)Months between audits for each rating. Make sure every process is still covered within your full cycle.6 / 12 / 24
Process / areaOne QMS process, matching the name on your process map. Add shifts or sites as separate rows if they run differently.Purchasing and supplier control
Clauses coveredThe requirements this audit will sample, so you can show the whole standard is covered.8.4
Risk / importanceHigh, Medium or Low, based on the importance of the process, changes, past findings and customer complaints.High
Last auditedDate of the last completed audit of this process. Leave blank if it has never been audited.2026-03-18
Next due (calculated)Last audited plus the interval. Do not type over it.2026-09-18
Independent?No if the lead auditor works in or is responsible for the process. Reassign those rows.Yes

Common mistakes

Frequently asked questions

How often should each process be audited?

ISO 9001 does not set a frequency. Base it on importance, changes and past results. Many companies audit every process at least once a year and higher-risk ones more often; IATF 16949 also requires every QMS process to be covered over each three-year period.

What is the difference between an audit programme and an audit plan?

The programme is the schedule of all audits over a period, like this sheet. An audit plan covers one audit: scope, criteria, time, auditors and who will be interviewed.

Can the quality manager audit document control?

Not if they own it. Auditors should not audit their own work. Use another trained auditor or an external auditor for the quality team’s own processes.

What counts as the last audited date?

The date the audit was carried out, not the date findings were closed. Track finding closure in your corrective action log.

Why does a row say Not yet audited?

The last audited date is blank, so there is nothing to add an interval to. Schedule a first audit and enter the date when it is done.

See also

COPLAIN AI PLATFORM

Generate yours automatically from your existing docs

Coplain’s Auditor Review checks your procedures against ISO 9001 before the audit, so the auditors on this schedule start from a clean set of documents.

Generate yours automatically with Coplain →

Related Tools & Templates