How to Create a Process Flow Diagram for Manufacturing

To create a process flow diagram, set the scope from receiving to shipping, walk the real process, and draw every step in order: operations, inspections, moves, storage and decisions. Give each step a number, and show rework, scrap and repair loops, not just the happy path. Note the product and process characteristics made or checked at each step. Then use those same step numbers in the PFMEA and the control plan, so the three documents stay linked. The steps below follow that order, and the Example works one through.

By Coplain Team

Last updated

Step by step

  1. Set the scope and the team — decide where the flow starts and ends. For a part, that is usually receipt of material to shipment of finished goods. Pull in the people who run the process: an operator, a setup technician, quality and manufacturing engineering. A SIPOC diagram is a quick way to agree on the boundaries first.
  2. Walk the process and list every step — go to the floor and follow a part from start to finish. Write down each operation, inspection, move, wait and storage point in the order it happens. Record what actually happens, including the informal steps nobody wrote down, then decide later whether they belong.
  3. Number the steps and pick consistent symbols — give each step a number in tens (10, 20, 30) so you can insert steps later without renumbering. Use one symbol set and add a legend: commonly a circle for an operation, a square for an inspection, an arrow for a move, a triangle for storage, and a diamond for a decision.
  4. Add decisions, rework and scrap paths — after every inspection, show what happens to a failed part: back to an earlier step for rework, to a repair step, to a hold area for review, or to scrap. A flow with no rework loops usually hides where defects go. Mark the material review or NCR point.
  5. List characteristics at each step — beside each operation, note the product characteristics it creates (a diameter, a weld, a torque) and the process characteristics that drive them (spindle speed, temperature, pressure). Flag special characteristics your customer designates. These lists become the starting rows of the PFMEA.
  6. Link it to the PFMEA and control plan — use the same step numbers and names in the PFMEA worksheet and the control plan. Every step on the flow should appear in the PFMEA, and every control in the control plan should point back to a step. How to do a PFMEA covers the next stage.
  7. Review, release and keep it current — have the team check the diagram against the floor once more, then release it under document control with a revision. Update it whenever the process changes, and update the PFMEA and control plan at the same time.

Why the process flow comes first

In automotive advanced product quality planning (APQP), the process flow chart is one of the first process design outputs, and the PFMEA and control plan are built from it. IATF 16949 lists a manufacturing process flow chart among the outputs of process design. The reason is practical: you cannot analyse failure modes for a step you never listed, and you cannot control a characteristic you never wrote down. The quality core tools guide, the pillar for this cluster, shows how the documents connect.

A process flow diagram is different from a value stream map. A value stream map shows material and information flow with times and inventory to find waste. A process flow diagram lists every step and its characteristics to find risk. Many teams make both from the same floor walk.

How much detail to show

Show every step where the product changes, is checked, is moved or waits, plus every decision. Do not split a single machining operation into its individual tool moves; that belongs on the work instruction. One page per part family is a good target. If the flow will not fit, split it into linked sub-flows (for example, machining and assembly) rather than shrinking the text.

Adding cycle times to each step turns the diagram into a capacity check. The cycle time calculator and takt time calculator help you see which step limits output.

Who should be in the room

A flow diagram drawn by one engineer usually shows the process as designed, not as run. Include at least one operator from each shift, because shifts often run the same step differently, and include the person who handles rejected parts, because rework paths are the part most often missing. Bring material handling in if parts move between buildings or wait in staging. Review the draft with the people who will write the PFMEA and control plan, so the step names and numbers work for them before anything is built on top.

Worked examples

Example: A fictional turned-and-plated shaft: step list and a capacity check

  1. Step list: 10 Receive bar stock; 20 Receiving inspection (material certs); 30 Store raw material; 40 CNC turn; 50 In-process check (OD, length); 60 Deburr; 70 Send to plating (outside process); 80 Plating receipt check (thickness); 90 Final inspection; 100 Pack and ship.
  2. Reject paths: from 50, rework back to 40 or scrap; from 80, return to the plater; from 90, hold for NCR review.
  3. Cycle times per part: 40 Turn = 95 s; 50 Check = 20 s; 60 Deburr = 40 s; 90 Final = 30 s.
  4. Customer demand 1,600 parts a week, 5 shifts of 7.5 h available: takt = (5 × 7.5 × 3,600) ÷ 1,600 = 135,000 ÷ 1,600 = 84.4 s.
  5. Step 40 at 95 s is above takt (95 > 84.4), so one lathe cannot meet demand: 135,000 ÷ 95 = 1,421 parts a week.

Result: Example result: the flow shows 10 steps with three reject paths, and the cycle times show turning (step 40) is the constraint. The team plans a second lathe or a shorter cycle before launch, and the PFMEA starts from step 10. All values are example values.

Common mistakes

Frequently asked questions

What is the difference between a process flow diagram and a flowchart?

A flowchart can describe any logic. A manufacturing process flow diagram is a specific flowchart of operations, inspections, moves and storage for a product, usually with step numbers and characteristics.

What symbols are used in a process flow diagram?

Common sets use a circle for an operation, a square for inspection, an arrow for transport, a triangle for storage and a diamond for decisions. Use one set consistently and include a legend.

Is a process flow diagram required for PPAP?

In the AIAG PPAP manual, a process flow diagram is one of the standard submission elements, and customers usually expect it. Check your customer’s requirements for the submission level.

What software should I use?

Any tool that produces a clear, revision-controlled document works: a spreadsheet, a diagramming tool or a drawing on a template. Readability and consistency with the PFMEA matter more than the software.

How is it different from a value stream map?

A value stream map shows flow, time and inventory to find waste. A process flow diagram lists every step and its characteristics to find risk and plan controls.

Sources

  1. Advanced Product Quality Planning and Control Plan (APQP) reference manual, AIAG
  2. Production Part Approval Process (PPAP) reference manual, AIAG
  3. AIAG & VDA FMEA Handbook (2019), AIAG and VDA
  4. IATF 16949:2016 (clause 8.3.5.2, manufacturing process design output), International Automotive Task Force (IATF)

See also

COPLAIN AI PLATFORM

Generate yours automatically from your existing docs

Coplain turns each step of your process flow into a numbered work instruction, using the same step numbers as your PFMEA and control plan.

Generate yours automatically with Coplain →

Related Tools & Templates