FREE TOOL

Cycle Time and Production Capacity Calculator

Enter a known cycle time, or a timed run and the cycles completed. Add parts per cycle, machines, shift pattern and planned efficiency to get capacity per hour, shift, day and week. Add weekly demand to see utilization and takt time.

Cycle time and capacity calculator

What do you have?
Time between finished cycles (s)
Cavities or fixture positions
Running the same part
After breaks (h)
Whole shifts
1 to 7
Target OEE, or 100 for theoretical (%)
Parts required per week
Cycle time
45 s
Time per part
22.5 s
Capacity per hour
136
Capacity per shift
1020
Capacity per day
2040
Capacity per week
10200
Utilization
88.24 %
Takt time
30 s
Intermediate steps
StepFormulaValue
Effective time per partCT / (parts per cycle × machines) = 45 / (2 × 1)22.5 s
Capacity per hour3600 / 22.5 × 85%136
Capacity per shift136 × 7.5 h1020
Capacity per day1020 × 2 shifts2040
Capacity per week2040 × 5 days10200
Utilizationu = demand / capacity = 9000 / 1020088.24 %
Takt timeTakt = 270000 s / 900030 s

Formulas used

Observed cycle time
CT = run time / cycles completed
Effective time per part
CT / (parts per cycle × machines)
Capacity per hour
3600 / time per part × planned efficiency
Capacity per week
per hour × hours per shift × shifts per day × days per week
Utilization
u = weekly demand / weekly capacity
Takt time
Takt = available time per week / weekly demand

Assumptions and limits

  • Cycle time is the time between finished cycles of one machine or station, including load and unload.
  • Parallel machines run the same part at the same cycle time.
  • Planned efficiency scales theoretical capacity to an expected one. A target OEE is a common choice; 100% gives theoretical capacity.
  • Available time is hours per shift × shifts × days, with breaks already removed from hours per shift.
  • Utilization above 100% means demand exceeds expected capacity. Close to 100%, queues and lead times grow quickly in practice.

Worked example

Example: a two-cavity mould completes 80 cycles in a timed 60-minute run. One machine runs two 7.5-hour shifts, five days a week, at a planned efficiency of 85%. Weekly demand is 9,000 parts.

Intermediate steps
StepFormulaValue
Observed cycle timeCT = 60 min × 60 / 80 cycles45 s
Effective time per partCT / (parts per cycle × machines) = 45 / (2 × 1)22.5 s
Capacity per hour3600 / 22.5 × 85%136
Capacity per shift136 × 7.5 h1020
Capacity per day1020 × 2 shifts2040
Capacity per week2040 × 5 days10200
Utilizationu = demand / capacity = 9000 / 1020088.24 %
Takt timeTakt = 270000 s / 900030 s

Result: Cycle time is 45 s, expected capacity is 10200 parts per week, and demand uses 88.2% of it.

How to measure cycle time and capacity

Measure cycle time, don't assume it

Time a run of many cycles and divide by the number completed. This averages out short stops and load variation that a single stopwatch reading misses. Use the routing or programme time only as a check.

Theoretical vs expected capacity

At 100% efficiency the result is the most the equipment can make if it never stops. Real output is lower because of breakdowns, changeovers, slow cycles and scrap. Using your measured OEE as planned efficiency gives a capacity you can plan against.

Compare with demand

Utilization shows how much of expected capacity the demand uses. Takt time shows the pace demand requires. If time per part is longer than takt, the equipment cannot keep up without more machines, more shifts or a shorter cycle.

When the cycle is too slow

Look at the cycle broken into elements: load, process, unload. Moving load and unload outside the machine cycle, adding a cavity or fixture position, or splitting the work across stations can each shorten time per part. The line balancing calculator helps with the last option.

Common mistakes

  • Planning at 100% efficiency. No line runs without stops. Use measured OEE or a realistic target.
  • Confusing cycle time with lead time. Cycle time is how often a part comes off; lead time is how long one part spends in the whole process.
  • Forgetting parts per cycle. A four-cavity tool makes four parts per cycle. Leaving it at one understates capacity by 75%.
  • Counting breaks as available time. Enter hours per shift after breaks, or capacity will be overstated.
  • Treating 99% utilization as fine. Near full utilization, small disruptions cause long queues. Leave headroom.

Frequently asked questions

How do you calculate cycle time?

Divide production time by the number of cycles completed in it. 80 cycles in 60 minutes is 3,600 s / 80 = 45 s per cycle.

How do you calculate production capacity?

Divide available time by the time per part, then apply planned efficiency. For one machine making 2 parts every 45 s at 85% efficiency: 3,600 / 22.5 × 0.85 = 136 parts per hour.

What is the difference between cycle time and takt time?

Cycle time is how fast you can make a part. Takt time is how fast demand requires it. Time per part must be at or below takt to meet demand.

Should I use OEE as planned efficiency?

If you measure OEE, it is a good basis because it already includes availability, performance and quality losses. If you don't, start from your actual output divided by theoretical capacity over a recent period.

What utilization should I plan for?

There is no single right number. Higher utilization means less spare capacity to absorb breakdowns and demand spikes, so lead times grow sharply as it nears 100%.

Sources

  • Hopp, W. J. and Spearman, M. L., Factory Physics, Waveland Press — capacity, utilization and cycle time.
  • Groover, M. P., Automation, Production Systems, and Computer-Integrated Manufacturing, Pearson — production rate and plant capacity.
  • Rother, M. and Shook, J., Learning to See, Lean Enterprise Institute — takt time.

Results are computed in your browser from the published formulas named above. They are an engineering aid, not a substitute for the governing standard, your drawing, or your customer's requirements.

Related Tools & Templates