CNC Machine Setup Work Instruction Example

A CNC machine setup work instruction tells the setter how to take a machine from the last job to an approved first part on the next one: check the documents, clear the machine, mount and indicate the fixture, load tools and set offsets, prove the program, and get first-piece sign-off before production. Below is a complete example for a fictional shop’s vertical machining center, with numbered steps, key points, reasons, safety callouts and acceptance criteria, plus a free .docx to edit. Every spec value in it is an example value, not a recommendation.

By Coplain Team

Last updated

What a CNC setup involves

A setup covers everything between the last good part of one job and the first approved part of the next: tearing down the old fixture, mounting and aligning the new one, loading and measuring tools, setting the work offset, loading and proving the program, and inspecting the first piece. Most of the risk sits in a few places. The program or drawing may be the wrong revision, a tool length offset may be entered against the wrong tool, or the work offset may be set to a point that is not the drawing datum. Any of those can scrap a run or crash the spindle.

A setup work instruction fixes the order of those tasks and puts a check at each risky point, so two setters on two shifts set the machine the same way. It is written for one machine type or cell and reused for every job on it. The values that change job to job, such as tool list, fixture location and datum, live on the job’s setup sheet, and the instruction tells the setter where to find them and how to check them.

Setup sheet or work instruction?

The setup sheet answers “what” for one part number: which fixture, which tools in which pockets, which datum, which program. The work instruction answers “how” for every part on that machine: the method, the checks and the sign-offs. Keeping them apart means a new job needs a new setup sheet, not a rewritten instruction. Cutting data belongs on the setup sheet or in the program, set by the programmer. The speeds and feeds calculator is a starting point for that, not a substitute for the programmer’s values.

Example: Vertical Machining Center Job Setup

Example This work instruction is for Example Manufacturing Co., a fictional contract machine shop. Document numbers, tolerances and override settings are example values, not recommendations. Use the values on your own setup sheet, machine manual and procedures.

Download this example (.docx)

Document control
Document no.WI-MCH-014 (example)
RevisionB
Applies to3-axis vertical machining centers in Cell 2
OwnerManufacturing engineering
Approved byQuality manager (signature on master copy)
TrainingSetters signed off for VMC setup on the skills matrix

Tools, materials and PPE

Steps

  1. Check the job packet. Compare the revision on the drawing, setup sheet and program header with the traveler.
    Key point: All four revisions match. If any differs, stop and call the lead before touching the machine.
    Reason: A program or drawing at the wrong revision can turn out a whole run of parts that meet the wrong requirement.
  2. Clear and clean the machine. Remove the previous fixture and any tools not on the new setup sheet. Clean chips from the table, T-slots and fixture seats.
    Key point: Return removed tools to the crib, tagged with the job they came from.
    Reason: A chip under a fixture tilts it, and every feature machined from it shifts.Safety: Put the machine in setup mode with the spindle stopped before reaching into the work envelope. Clear chips with a brush or hook, never bare hands or compressed air.
  3. Mount and indicate the fixture. Clamp the vise or fixture at the location on the setup sheet. Sweep the locating face along the X axis with the dial test indicator and adjust until it is in tolerance.
    Key point: Within 0.01 mm over the jaw length (example value; use the tolerance on your setup sheet). Re-check after final clamping.
    Reason: A fixture out of square tilts every feature relative to the datums on the drawing.Safety: Use the hoist or lift assist for fixtures over the weight limit. Keep fingers clear of the clamping points.
  4. Load tools and set length offsets. Load each tool in the pocket on the setup sheet. Measure each length on the presetter or with the probe and enter it in the matching offset register.
    Key point: Read back tool number, pocket and offset number for every tool. They must match the setup sheet.
    Reason: A length offset entered against the wrong tool drives the cutter into the part or fixture.Safety: Handle cutters by the holder. Remove gloves before running the spindle.
  5. Set the work offset. Find the datum named on the setup sheet with the probe or an edge finder and enter it in the work offset on the setup sheet, for example G54.
    Key point: Confirm the setup-sheet datum is the same feature as the drawing datum before you touch off.
    Reason: An offset set to the wrong corner or face moves every feature by the same error.
  6. Prove the program. Load the program and confirm its number and revision on the control. Run it in graphics, then dry-run it with the work offset raised in Z by 50 mm and rapid override at 25% (example values).
    Key point: Watch each tool change and approach. Keep one hand on feed hold during the dry run.
    Reason: Offset and program errors show up in air instead of in the part or the fixture.Safety: Run with the door closed and the interlocks working. Never bypass an interlock to watch the cut.
  7. Cut and measure the first piece. Run the first part in single block through each new tool. Measure every characteristic on the first-piece checklist with the gauges on the setup sheet.
    Key point: Write the measured value for each characteristic, not a tick. Check gauge calibration dates first.
    Reason: Recorded values show the setup is centered in tolerance, not just inside it, and give the next setter a reference.
  8. Get first-piece approval. Give the part and the filled checklist to the inspector or another authorized person for review and sign-off.
    Key point: No production parts until the first piece is signed off.
    Reason: An independent check catches errors the setter is too close to see.
  9. Record and release. Write any offset or program changes on the setup sheet, sign the traveler and release the machine to production.
    Key point: Changes to the program go back to programming. Do not save edits on the control without approval.
    Reason: The next setup starts from what worked, and the program master stays controlled.

Acceptance criteria

How to adapt this example

Copy the steps into the blank work instruction template, or edit the .docx above. Start from your own setup, not from this page. Watch your best setter run a job, write down what they actually do and in what order, then use the example to check you have a key point and a reason for each step. The how to write a work instruction guide covers the method.

The tap drill chart helps when checking drill sizes on the tool list, and the unit converter helps when a drawing and a machine work in different units. To turn this instruction into a one-page sheet at the machine, see job aid vs work instruction vs SOP.

Common mistakes

Frequently asked questions

What should a CNC setup work instruction include?

Document control, the tools and PPE needed, numbered steps from checking the job packet to releasing the machine, a key point and reason for each step, safety callouts at the steps where hazards occur, and acceptance criteria for the setup.

Is a setup sheet the same as a work instruction?

No. A setup sheet lists the job-specific fixture, tools, offsets and program for one part. The work instruction describes the setup method for every job on that machine type.

Who should approve a CNC setup?

Your quality plan sets that. Commonly the setter does the setup and an inspector or another authorized person approves the first piece before production.

Are the tolerances in this example recommendations?

No. They are example values for a fictional shop. Use the tolerances and settings from your own setup sheet, drawing and machine manual.

How often should a setup work instruction be reviewed?

Whenever the machine, control, fixturing method or inspection requirement changes, after a setup-related nonconformance, and on your normal document review cycle.

Sources

  1. ISO 9001:2015 Quality management systems — Requirements (clause 8.5.1, control of production), ISO
  2. 29 CFR 1910.212, General requirements for all machines, U.S. Occupational Safety and Health Administration
  3. Machinery’s Handbook, Industrial Press

See also

COPLAIN AI PLATFORM

Generate yours automatically from your existing docs

Turn your real work instruction into an audit-ready job aid in Coplain. Upload your setup procedure and Coplain drafts the numbered steps, key points and checks for your team to review.

Generate yours automatically with Coplain →

Related Tools & Templates